 Do you have to sue all the parties involved in the construction when bringing a legal claim for defects in a home?

No compulsory joinder of defendants

Once a lawsuit has been filed against the parties involved in the construction whom the expert report has identified as “liable” for the defects in the home, it is quite common for the defendants to ask for other parties involved in the construction (architects, quantity surveyors, the building contractor, subcontractors…) to be brought in, by requesting “compulsory joinder of defendants” (litisconsorcio pasivo necesario). This is because each party considers that it is not responsible and blames the other professionals instead. So, do you have to sue them all?

The case law of the Supreme Court has resolved this question, denying that it is necessary to sue everyone, on two grounds:

*On the one hand, the injured party is free to sue whichever party or parties it sees fit, the only drawback being that if, after proceedings have been brought against a particular person, the evidence leads to the conclusion that that person is not liable, they will be acquitted; otherwise, they will be found liable.

* On the other hand, the reasoning is that, where it is not possible to establish the specific fault of each party involved in the construction of the defective building, the ten-year liability is joint and several, and one of the typical effects of joint and several obligations, under article 1144 of the Civil Code, is that “the creditor may proceed against any of the joint and several debtors or against all of them simultaneously“. This approach is reinforced by stating that a judgment declaring joint and several liability and ordering the sole defendant to pay does not prejudge the internal relationship between the jointly and severally liable parties, which will be dealt with as a separate matter between the various obligors, under article 1145.                      

Third-party joinder requested by other defendants.

               That said, through the mechanism of “third-party joinder” (intervención provocada) permitted by the Civil Procedure Act (LEC) in these cases, the defendants can sometimes force other parties to be brought into the proceedings so that the case is not decided in their absence, since the judgment could affect them. In that case, the claimant may either object to the participation of those other parties involved in the construction, or accept it and extend the lawsuit to include them.

               For this reason, claimants are under no obligation to sue  all of the many parties involved in the works from the outset – quantity surveyor,  subcontractors, suppliers, etc. – without prejudice to whatever may be decided in the proceedings.

If you have any questions, consult us. 

 

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Responsable » DPCON RECLAMACIONES JUDICIALES SL
Finalidad » Prestación de servicios requeridos
Legitimación » tu consentimiento
Destinatarios » No se cederán datos a terceros.
Derechos » Tiene derecho de acceso, rectificación y supresión

Related articles

DON’T HESITATE TO CONSULT US!

CUSTOM BUDGETS

12 + 7 =

GDPR-LSSI

The information you submit will be added to a file owned by DPCON RECLAMACIONES JUDICIALES S.L. It will be used solely to process your data and handle your request, in compliance with Regulation (EU) 2016/679 (GDPR), Organic Law 3/2018 (LOPDGDD) and Royal Decree 1720/2007. Your data will not be shared with third parties except when legally required, and will be retained until you request deletion.
You may exercise your rights of access, rectification, erasure, portability, restriction, objection and withdrawal of consent at any time by writing to dpcon@dpcon.es.

Contact

Telephones: 911 61 01 65 / 646 567 732

Email: dpcon@dpcon.es

Headquarters: Paseo de la Castellana 257, 1º Sur
CP 28046, Madrid

SERVICE ALL OVER SPAIN

WhatsApp